SOLAR · SOUTHEASTSolar project 151, Columbia County
Solar project 151, Columbia County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Columbia County, Florida, connecting to Duke Energy Florida.
Queue statusIn planning
- PlanningQueued Jul 2016 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2019 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 151
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Radiant Switching Station
- Location
- Columbia County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- NRIS and ERIS
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 27 July 2016
- Proposed online date
- December 2019
Location
Marker shows the centre of Columbia County; the queue data does not give exact sites.
Other requests in Columbia County
- Solar project 152, Columbia CountySolar · 74.9 MW · built
- Solar project 148, Columbia CountySolar · 74.9 MW · built
- Solar project 169, Columbia CountySolar · 74.5 MW · built
- Battery storage project 379, Columbia CountyBattery storage · 30.0 MW · built
- Battery storage project 617, Columbia CountyBattery storage · 200 MW · withdrawn
- Solar project 202A, Columbia CountySolar · 74.9 MW · withdrawn
- Solar project 153, Columbia CountySolar · 74.9 MW · withdrawn
- Solar project 441, Columbia CountySolar · 74.5 MW · withdrawn
- Solar project 435, Columbia CountySolar · 74.5 MW · withdrawn
- Solar project 440, Columbia CountySolar · 74.5 MW · withdrawn
- Solar project 170, Columbia CountySolar · 74.5 MW · withdrawn
- Solar project 436, Columbia CountySolar · 74.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem