πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

El Centro 1

El Centro 1 is a 375 MW solar request withdrawn in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandonedMay 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
286
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Southwest Power Link 500kV line
Location
Imperial County, California
Technology
Solar: 375 MW
Total requested
375 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
20 December 2007
Proposed online date
July 2012
Withdrawn
May 2008

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Imperial County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem