United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· SPP

Other project GEN-2017-176, Castro County

Other project GEN-2017-176, Castro County is a 300 MW other request withdrawn in the SPP interconnection queue, in Castro County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedJan 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-176
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Newhart 230kV Substation
Location
Castro County, Texas
Technology
Solar: 300 MW Β· Wind
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 November 2017
Proposed online date
December 2026
Withdrawn
January 2023

Location

Marker shows the centre of Castro County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Castro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem