BATTERY STORAGE · ERCOT

Guinness BESS

Guinness BESS is a 101 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Williamson County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0352
Grid region
ERCOT (Texas)
Developer
Momentum Energy Storage Partners,LLC
Connection point (POI)
Tap 138kV 7520 BERTRA - 7522 ANDICE
Location
Williamson County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
25 July 2022
Proposed online date
April 2027

Location

Marker shows the centre of Williamson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Williamson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem