Rio Grand Valley Element Fuels Power

Rio Grand Valley Element Fuels Power is a 230 MW other request in interconnection study in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0515
Grid region
ERCOT (Texas)
Developer
Element H2Gen, LLC
Connection point (POI)
Tap 138kV 59450 Waterport Substation - 5789 Southmost Sub
Location
Cameron County, Texas
Technology
Hydrogen: 230 MW
Total requested
230 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
13 June 2024
Proposed online date
July 2027

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County