United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· MISO

Solar project J2103, Jasper County

Solar project J2103, Jasper County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Jasper County, Texas, connecting to ENTERGY TEXAS, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2103
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY TEXAS, INC.
Connection point (POI)
Buna SW to Call Transmission Line
Location
Jasper County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process
Queue status
Withdrawn
Entered queue
1 September 2021
Proposed online date
October 2024
Withdrawn
December 2021

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem