SOLAR + STORAGE Β· MISO

Solar + storage project J2976, Jasper County

Solar + storage project J2976, Jasper County is a 50.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Jasper County, Texas, connecting to EAST TEXAS ELECTRIC COOPERATIVE, INC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2976
Grid region
MISO (Midcontinent)
Utility / transmission owner
EAST TEXAS ELECTRIC COOPERATIVE, INC.
Connection point (POI)
Mill Creek SW Station 138 kV
Location
Jasper County, Texas
Technology
Solar: 50.0 MW Β· Battery
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
May 2025
Withdrawn
July 2025

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem