🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Turin TxHSR TPSS HN-6

Turin TxHSR TPSS HN-6 is a 50.0 MW other request in interconnection study in the ERCOT interconnection queue, in Grimes County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0001
Grid region
ERCOT (Texas)
Developer
Texas Central Rail Holdings, LLC
Connection point (POI)
8 Crutchfield 138kV
Location
Grimes County, Texas
Technology
Other: 50.0 MW
Total requested
50.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 September 2019
Proposed online date
July 2028

Location

Marker shows the centre of Grimes County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Grimes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem