πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 20.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Somerset County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
928
Grid region
ISO-NE (New England)
Connection point (POI)
34.5 kV bus at CMP's Lakewood Substation in Madison, Maine
Location
Somerset County, Maine
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
9 October 2019
Proposed online date
April 2027
Withdrawn
November 2023

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem