United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

GAS Β· SPP

Gas project GEN-2012-003, Stevens County

Gas project GEN-2012-003, Stevens County is a 22.5 MW gas request withdrawn in the SPP interconnection queue, in Stevens County, Kansas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2012-003
Grid region
SPP (Southwest Power Pool)
Connection point (POI)
Tap Hugoton - Rolla 69kV
Location
Stevens County, Kansas
Technology
Gas: 22.5 MW
Total requested
22.5 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
22 March 2012
Proposed online date
December 2013

Location

Marker shows the centre of Stevens County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Stevens County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem