Colver Power

Colver Power is a 6.0 MW coal request built and operating in the PJM interconnection queue, in Cambria County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Jun 1997 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2000 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
A10
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Glory 115 kV
Location
Cambria County, Pennsylvania
Technology
Coal: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Operational
Entered queue
2 June 1997
Proposed online date
January 2000
Came online
January 2000

Location

Marker shows the centre of Cambria County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Cambria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem