Coal project G543, Beaver County

Coal project G543, Beaver County is a 50.0 MW coal request built and operating in the MISO interconnection queue, in Beaver County, Pennsylvania.

Queue statusOperating
  1. PlanningQueued Sep 2005 (completed)
  2. ConsentedJan 2006 (completed)
  3. Construction (completed)
  4. OperatingDec 2005 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G543
Grid region
MISO (Midcontinent)
Connection point (POI)
FE Mansfield Three
Location
Beaver County, Pennsylvania
Technology
Coal: 50.0 MW
Total requested
50.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
2 September 2005
Agreement signed
13 January 2006
Proposed online date
December 2005
Came online
December 2005

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.