Coal project G541, Beaver County

Coal project G541, Beaver County is a 50.0 MW coal request built and operating in the MISO interconnection queue, in Beaver County, Pennsylvania.

Queue statusOperating
  1. PlanningQueued Sep 2005 (completed)
  2. ConsentedJan 2006 (completed)
  3. Construction (completed)
  4. OperatingOct 2006 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G541
Grid region
MISO (Midcontinent)
Connection point (POI)
FE Mansfield Unit One
Location
Beaver County, Pennsylvania
Technology
Coal: 50.0 MW
Total requested
50.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
2 September 2005
Agreement signed
13 January 2006
Proposed online date
October 2006
Came online
October 2006

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.