SOLAR · PJMChoptank Solar and Storage
Choptank Solar and Storage is a 100 MW solar request withdrawn in the PJM interconnection queue, in Dorchester County, Maryland, connecting to DPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-358
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Developer
- RWE Solar Development, LLC
- Connection point (POI)
- Airey-Vienna 69 kV
- Location
- Dorchester County, Maryland
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- December 2023
- Withdrawn
- November 2025
Location
Marker shows the centre of Dorchester County; the queue data does not give exact sites.
Other requests in Dorchester County
- Egypt Road SolarSolar · 51.1 MW · agreement signed
- SBC SolarSolar + storage · 10.0 MW · agreement signed
- GGC SolarSolar + storage · 2.7 MW · agreement signed
- Solar project AH2-096, Dorchester CountySolar · 19.5 MW · in study
- New Market SolarSolar · 50.0 MW · suspended
- Richfield Solar and StorageSolar · 50.0 MW · built
- Constellation Solar Maryland II, LLC Solar FacilitySolar · 3.4 MW · built
- Gas project G28, Dorchester CountyGas · 390 MW · withdrawn
- Battery storage project AF2-409, Dorchester CountyBattery storage · 100 MW · withdrawn
- Solar project AE2-209, Dorchester CountySolar · 56.0 MW · withdrawn
- Solar project AG2-181, Dorchester CountySolar · 28.0 MW · withdrawn
- Solar project AG2-592, Dorchester CountySolar · 28.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem