πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

ONSHORE WIND Β· ISO-NE

Longfellow Wind

Longfellow Wind is a 50.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Oxford County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2007 (completed)
  2. Withdrawn / abandonedDec 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
215
Grid region
ISO-NE (New England)
Connection point (POI)
CMP 115 kV Rumford Substation
Location
Oxford County, Maine
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
24 May 2007
Proposed online date
December 2013
Withdrawn
December 2011

Location

Marker shows the centre of Oxford County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Oxford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem