United States › Grid › Interconnection queues › California
ONSHORE WIND · CAISOSolano Wind Project - Phase 3 (230KV)
Solano Wind Project - Phase 3 (230KV) is a 128 MW onshore wind request built and operating in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.
Request details
- Queue ID
- 108
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Lambie-Contra Costa 230 kV
- Location
- Solano County, California
- Technology
- Wind: 128 MW
- Total requested
- 128 MW
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 9 June 2006
- Agreement signed
- 16 December 2008
- Proposed online date
- March 2011
- Came online
- March 2012
Location
Marker shows the centre of Solano County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Solano County
- CorbyBattery storage · 314 MW · agreement signed
- Montezuma IIWind + storage · 132 MW · agreement signed
- Solano 4 WindOnshore wind · 92.4 MW · agreement signed
- Montezuma (High Winds III)Wind + storage · 76.0 MW · agreement signed
- Corby 2Battery storage · 476 MW · in study
- TolenasBattery storage · 417 MW · in study
- BrushyBattery storage · 400 MW · in study
- High Winds StorageBattery storage · 121 MW · in study
- Toland Renewable Energy ParkOnshore wind · 108 MW · in study
- Arges BESSBattery storage · 102 MW · in study
- Shiloh IIIOnshore wind · 200 MW · built
- Shiloh Wind Farm IIOnshore wind · 150 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem