πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

BATTERY STORAGE Β· NYISO

Kce NY 34

Kce NY 34 is a 13.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Ulster County, New York, connecting to CHGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedFeb 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1317
Grid region
NYISO (New York)
Utility / transmission owner
CHGE
Developer
KCE NY 34, LLC
Connection point (POI)
13.8 kV Saugerties Substation
Location
Ulster County, New York
Technology
Battery: 13.0 MW
Total requested
13.0 MW
Queue status
Withdrawn
Entered queue
21 December 2021
Withdrawn
February 2022

Location

Marker shows the centre of Ulster County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Ulster County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem