United States › Grid › Interconnection queues › California

SOLAR · CAISO

Golden Hills Solar Farm

Golden Hills Solar Farm is a 70.0 MW solar request withdrawn in the CAISO interconnection queue, in Stanislaus County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
707
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Solado sub 115 KV bus
Location
Stanislaus County, California
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
July 2014
Withdrawn
May 2013

Location

Marker shows the centre of Stanislaus County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Stanislaus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem