OFW Solar Farm

OFW Solar Farm is a 75.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Shenandoah County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-086
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
OFW Solar Farm, LLC
Connection point (POI)
Mt. Jackson DP-Mt. Jackson 115 kV
Location
Shenandoah County, Virginia
Technology
Solar: 75.0 MW · Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
19 February 2025
Proposed online date
December 2022

Location

Marker shows the centre of Shenandoah County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Shenandoah County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem