United States › Grid › Interconnection queues › Oregon

ONSHORE WIND · WEST

Anderson Ranch Wind Farm

Anderson Ranch Wind Farm is a 100 MW onshore wind request withdrawn in the West interconnection queue, in Gilliam County, Oregon, connecting to NextEra Energy Resources, LLC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2002 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G97
Grid region
West (non-ISO utilities)
Utility / transmission owner
NextEra Energy Resources, LLC
Developer
NextEra Energy Resources, LLC
Connection point (POI)
Slatt - John Day 500 kV
Location
Gilliam County, Oregon
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
19 March 2002
Proposed online date
September 2002

Location

Marker shows the centre of Gilliam County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Gilliam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem