πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AH2-250, Bucks County

Solar project AH2-250, Bucks County is a 9.3 MW solar request withdrawn in the PJM interconnection queue, in Bucks County, Pennsylvania, connecting to PECO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedJul 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-250
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PECO
Connection point (POI)
TBD 13.2 kV
Location
Bucks County, Pennsylvania
Technology
Solar: 9.3 MW
Total requested
9.3 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 March 2022
Proposed online date
February 2024
Withdrawn
July 2024

Location

Marker shows the centre of Bucks County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Bucks County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem