United States › Grid › Interconnection queues › Pennsylvania
OTHER · PJMCroydon #11,12,21,22,31,32,41,42
Croydon #11,12,21,22,31,32,41,42 is a 6.5 MW other request built and operating in the PJM interconnection queue, in Bucks County, Pennsylvania, connecting to PECO.
Request details
- Queue ID
- E20
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PECO
- Connection point (POI)
- Croydon 230kV
- Location
- Bucks County, Pennsylvania
- Technology
- Oil: 6.5 MW
- Total requested
- 6.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 28 November 2000
- Proposed online date
- December 2002
- Came online
- December 2002
Location
Marker shows the centre of Bucks County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Bucks County
- Energy MountainBattery storage · 150 MW · suspended
- Ford MillGas · 605 MW · built
- Ford MillGas · 540 MW · built
- Ford MillGas · 101 MW · built
- Ford MillGas · 74.0 MW · built
- Other project J374, Bucks CountyOther · 30.0 MW · built
- Croydon Generating StationGas · 5.0 MW · built
- Exelon Epuron Solar Energy CenterSolar · 3.3 MW · built
- Westwood GenerationCoal · 2.5 MW · built
- Gas project S105, Bucks CountyGas · 1,200 MW · withdrawn
- Gas project G41, Bucks CountyGas · 750 MW · withdrawn
- Gas project G13, Bucks CountyGas · 600 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem