WIND + STORAGE · ISO-NE

Battery storage addition (see Q745)

Battery storage addition (see Q745) is a 24.4 MW wind + storage request withdrawn in the ISO-NE interconnection queue, in Franklin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
747
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Larrabee Road Station,345 kV
Location
Franklin County, Maine
Technology
Wind: 24.4 MW · Battery
Total requested
24.4 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 April 2018
Proposed online date
October 2021
Withdrawn
August 2019

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Franklin County