100MW Longview 1

100MW Longview 1 is a 100 MW gas request withdrawn in the West interconnection queue, in Cowlitz County, Washington, connecting to Avista Power, LLC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G44
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Power, LLC
Connection point (POI)
BPA's Longview Substation
Location
Cowlitz County, Washington
Technology
Gas: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
11 April 2001
Proposed online date
December 2001

Location

Marker shows the centre of Cowlitz County; the queue data does not give exact sites.