United States › Grid › Interconnection queues › Washington
GAS · WESTMint Farm Energy Center
Mint Farm Energy Center is a 320 MW gas request built and operating in the West interconnection queue, in Cowlitz County, Washington, connecting to Puget Sound Energy, Inc..
Request details
- Queue ID
- G4
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Puget Sound Energy, Inc.
- Connection point (POI)
- Longview 230 kV Substation
- Location
- Cowlitz County, Washington
- Technology
- Gas: 320 MW
- Total requested
- 320 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 28 July 2000
- Agreement signed
- 17 April 2002
- Proposed online date
- November 2007
Location
Marker shows the centre of Cowlitz County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Cowlitz County
- Onshore wind project T2-027, Cowlitz CountyOnshore wind · 199 MW · in study
- Battery storage project G0922, Cowlitz CountyBattery storage · 100 MW · in study
- Gas project 12-051, Cowlitz CountyGas · 375 MW · suspended
- Gas project G0213, Cowlitz CountyGas · 600 MW · withdrawn
- Enron Power MarketingGas · 600 MW · withdrawn
- Onshore wind project G1022, Cowlitz CountyOnshore wind · 530 MW · withdrawn
- Onshore wind project G1021, Cowlitz CountyOnshore wind · 530 MW · withdrawn
- Gas project 419, Cowlitz CountyGas · 375 MW · withdrawn
- Gas project G0258, Cowlitz CountyGas · 320 MW · withdrawn
- 310MW CardwellGas · 310 MW · withdrawn
- Onshore wind project C4-110, Cowlitz CountyOnshore wind · 199 MW · withdrawn
- Onshore wind project C3-033, Cowlitz CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem