GAS Β· WESTGas project G0213, Cowlitz County
Gas project G0213, Cowlitz County is a 600 MW gas request withdrawn in the West interconnection queue, in Cowlitz County, Washington.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2005 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G0213
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Longview Substation 230kV
- Location
- Cowlitz County, Washington
- Technology
- Gas: 600 MW
- Total requested
- 600 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 21 December 2005
- Proposed online date
- January 2012
Location
Marker shows the centre of Cowlitz County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Cowlitz County
- Onshore wind project T2-027, Cowlitz CountyOnshore wind Β· 199 MW Β· in study
- Battery storage project G0922, Cowlitz CountyBattery storage Β· 100 MW Β· in study
- Gas project 12-051, Cowlitz CountyGas Β· 375 MW Β· suspended
- Mint Farm Energy CenterGas Β· 320 MW Β· built
- Enron Power MarketingGas Β· 600 MW Β· withdrawn
- Onshore wind project G1022, Cowlitz CountyOnshore wind Β· 530 MW Β· withdrawn
- Onshore wind project G1021, Cowlitz CountyOnshore wind Β· 530 MW Β· withdrawn
- Gas project 419, Cowlitz CountyGas Β· 375 MW Β· withdrawn
- Gas project G0258, Cowlitz CountyGas Β· 320 MW Β· withdrawn
- 310MW CardwellGas Β· 310 MW Β· withdrawn
- Onshore wind project C4-110, Cowlitz CountyOnshore wind Β· 199 MW Β· withdrawn
- Onshore wind project C3-033, Cowlitz CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem