WIND + STORAGE Β· WEST

Wind + storage project Company MR, Lyon County

Wind + storage project Company MR, Lyon County is a 150 MW wind + storage request withdrawn in the West interconnection queue, in Lyon County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company MR
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Lyon County, Nevada
Technology
Wind: 150 MW Β· Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
24 March 2022
Proposed online date
March 2026

Location

Marker shows the centre of Lyon County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Lyon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem