Solar project 586, Umatilla County

Solar project 586, Umatilla County is a 6.0 MW solar request built and operating in the West interconnection queue, in Umatilla County, Oregon, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Jul 2014 (completed)
  2. ConsentedDec 2015 (completed)
  3. Construction (completed)
  4. OperatingTarget Jul 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
586
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
NorWest Energy 9, LLC
Connection point (POI)
Circuit 5W201, State Hospital, out of Buckaroo substation
Location
Umatilla County, Oregon
Technology
Solar: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed December 23, 2015
Queue status
Operational
Entered queue
2 July 2014
Agreement signed
23 December 2015
Proposed online date
July 2018

Location

Marker shows the centre of Umatilla County; the queue data does not give exact sites.