πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Ses Solar Two)

Ses Solar Two) is a 300 MW solar request withdrawn in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2005 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
78
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Imperial Valley Sub 230kV Bus
Location
Imperial County, California
Technology
Solar: 300 MW
Total requested
300 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 August 2005
Proposed online date
May 2012
Withdrawn
March 2012

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Imperial County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem