SOLAR Β· PJM

Solar project AH1-505, Mercer County

Solar project AH1-505, Mercer County is a 7.5 MW solar request withdrawn in the PJM interconnection queue, in Mercer County, Pennsylvania, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-505
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Wheatland 12.47 kV
Location
Mercer County, Pennsylvania
Technology
Solar: 7.5 MW
Total requested
7.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
June 2024
Withdrawn
September 2023

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem