United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

Ashford Wind

Ashford Wind is a 19.9 MW onshore wind request withdrawn in the NYISO interconnection queue, in Cattaraugus County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
297
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Ashford Wind Farm, LLC
Connection point (POI)
Otto-West Valley 34.5kV
Location
Cattaraugus County, New York
Technology
Wind: 19.9 MW
Total requested
19.9 MW
Queue status
Withdrawn
Entered queue
16 May 2008
Withdrawn
March 2010

Location

Marker shows the centre of Cattaraugus County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Cattaraugus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem