ONSHORE WIND · ERCOT

Espiritu Wind

Espiritu Wind is a 25.2 MW onshore wind request built and operating in the ERCOT interconnection queue, in Cameron County, Texas.

Queue statusOperating
  1. PlanningQueued May 2015 (completed)
  2. ConsentedJan 2020 (completed)
  3. Construction (completed)
  4. OperatingJun 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
17INR0031
Grid region
ERCOT (Texas)
Developer
Acciona
Connection point (POI)
8640 Kelvin 138kV
Location
Cameron County, Texas
Technology
Wind: 25.2 MW
Total requested
25.2 MW
Study phase
IA
Queue status
Operational
Entered queue
18 May 2015
Agreement signed
29 January 2020
Proposed online date
April 2021
Came online
June 2021

Location

Marker shows the centre of Cameron County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cameron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem