Dunkirk Unit 3 & 4

Dunkirk Unit 3 & 4 is a 370 MW gas request withdrawn in the NYISO interconnection queue, in Chautauqua County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2015 (completed)
  2. Withdrawn / abandonedJun 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
524
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Dunkirk Power LLC
Connection point (POI)
Dunkirk 230kV
Location
Chautauqua County, New York
Technology
Gas: 370 MW
Total requested
370 MW
Queue status
Withdrawn
Entered queue
17 December 2015
Withdrawn
June 2020

Location

Marker shows the centre of Chautauqua County; the queue data does not give exact sites.