GAS Β· CAISO

NCC Hybrid Power

NCC Hybrid Power is a 444 MW gas request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedJan 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1055
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
San Luis Rey Substation 230 kV
Location
San Diego County, California
Technology
Gas: 384 MW Β· Battery: 60.0 MW
Total requested
444 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
June 2019
Withdrawn
January 2015

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.