SOLAR Β· PJMMansfield Solar
Mansfield Solar is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2011 (completed)
- Withdrawn / abandonedMar 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- X1-054
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PSEG
- Connection point (POI)
- Burlington 26kV
- Location
- Burlington County, New Jersey
- Technology
- Solar: 10.0 MW
- Total requested
- 10.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 31 March 2011
- Proposed online date
- March 2013
- Withdrawn
- March 2013
Location
Marker shows the centre of Burlington County; the queue data does not give exact sites.
Power plants in New Jersey Β· Transmission lines in New Jersey
Other requests in Burlington County
- NaesBattery storage Β· 5.0 MW Β· agreement signed
- Battery storage project AH2-127, Burlington CountyBattery storage Β· 18.0 MW Β· in study
- NJ Land Phase IISolar Β· 10.0 MW Β· suspended
- BurlingtonGas Β· 168 MW Β· built
- North Hanover Solar FarmSolar Β· 17.0 MW Β· built
- Burlington #10Gas Β· 16.0 MW Β· built
- Cedar LaneSolar Β· 15.0 MW Β· built
- Dix Solar FarmSolar Β· 13.0 MW Β· built
- Reeves Station Road SolarSolar Β· 11.0 MW Β· built
- Taylors Lane SolarSolar Β· 10.0 MW Β· built