🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · CAISO

Crocker Solar Power - Unit One

Crocker Solar Power - Unit One is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2010 (completed)
  2. Withdrawn / abandonedNov 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
617
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla-Tracy 115kV
Location
San Joaquin County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
22 March 2010
Proposed online date
May 2016
Withdrawn
November 2013

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem