πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

SOLAR Β· SPP

Solar project GEN-2022-061, Scotts Bluff County

Solar project GEN-2022-061, Scotts Bluff County is a 180 MW solar request withdrawn in the SPP interconnection queue, in Scotts Bluff County, Nebraska, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-061
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Stegall 230 kV substation
Location
Scotts Bluff County, Nebraska
Technology
Solar: 180 MW
Total requested
180 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
18 July 2022
Proposed online date
June 2028
Withdrawn
November 2023

Location

Marker shows the centre of Scotts Bluff County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Scotts Bluff County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem