United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
SOLAR Β· SPPSolar project GEN-2022-061, Scotts Bluff County
Solar project GEN-2022-061, Scotts Bluff County is a 180 MW solar request withdrawn in the SPP interconnection queue, in Scotts Bluff County, Nebraska, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-061
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Stegall 230 kV substation
- Location
- Scotts Bluff County, Nebraska
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 18 July 2022
- Proposed online date
- June 2028
- Withdrawn
- November 2023
Location
Marker shows the centre of Scotts Bluff County; the queue data does not give exact sites.
Other requests in Scotts Bluff County
- Solar project GEN-2024-374, Scotts Bluff CountySolar Β· 225 MW Β· in study
- Onshore wind project GI-0816, Scotts Bluff CountyOnshore wind Β· 204 MW Β· withdrawn
- Battery storage project GEN-2018-036, Scotts Bluff CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project GEN-2016-093, Scotts Bluff CountySolar Β· 70.0 MW Β· withdrawn
- Solar project GEN-2017-037, Scotts Bluff CountySolar Β· 20.0 MW Β· withdrawn
- Gas project GEN-2007-012N, Scotts Bluff CountyGas Β· 8.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem