SOLAR Β· NYISO

Barrington Solar

Barrington Solar is a 18.4 MW solar request withdrawn in the NYISO interconnection queue, in Yates County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1575
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
NJR Clean Energy Ventures III Corporation
Connection point (POI)
Porter's corner to Dundee 34.5kV Line, Line #594
Location
Yates County, New York
Technology
Solar: 18.4 MW
Total requested
18.4 MW
Queue status
Withdrawn
Entered queue
29 June 2023

Location

Marker shows the centre of Yates County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Yates County