SOLAR + STORAGE · PJMWA-Cohechton 1
WA-Cohechton 1 is a 3.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Wayne County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-285
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- W. Damascus 12.47 kV
- Location
- Wayne County, Pennsylvania
- Technology
- Solar: 3.0 MW · Battery
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 27 March 2020
- Proposed online date
- February 2023
- Withdrawn
- November 2023
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Wayne County
- Solar project AH2-094, Wayne CountySolar · 5.0 MW · in study
- Solar project AF2-294, Wayne CountySolar · 17.0 MW · suspended
- Waymart WFOnshore wind · 70.0 MW · built
- WaymartOnshore wind · 13.0 MW · built
- ArchbaldGas · 1.0 MW · built
- Gas project AB1-151, Wayne CountyGas · 575 MW · withdrawn
- Onshore wind project AD2-152, Wayne CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project P45A, Wayne CountyOnshore wind · 120 MW · withdrawn
- Onshore wind project V3-042, Wayne CountyOnshore wind · 84.0 MW · withdrawn
- Onshore wind project Q02, Wayne CountyOnshore wind · 80.0 MW · withdrawn
- Waymart Wind IIOnshore wind · 67.3 MW · withdrawn
- Onshore wind project AA2-069A, Wayne CountyOnshore wind · 64.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem