20 MW Solar Project #1

20 MW Solar Project #1 is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedJun 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
480
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Borrego Substation 69kV
Location
San Diego County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
16 March 2009
Proposed online date
June 2014
Withdrawn
June 2013

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.