BATTERY STORAGE Β· WEST

Battery storage project 17, Sacramento County

Battery storage project 17, Sacramento County is a 200 MW battery storage request withdrawn in the West interconnection queue, in Sacramento County, California, connecting to Sacramento Municipal Utility District.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
17
Grid region
West (non-ISO utilities)
Utility / transmission owner
Sacramento Municipal Utility District
Connection point (POI)
New switching station near Franklin 230kV Substation
Location
Sacramento County, California
Technology
Battery: 200 MW
Total requested
200 MW
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
27 January 2022
Proposed online date
April 2025

Location

Marker shows the centre of Sacramento County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Sacramento County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem