United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Silverleaf Solar II

Silverleaf Solar II is a 60.0 MW solar request withdrawn in the CAISO interconnection queue, in Imperial County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2011 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
875
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Imperial Valley Substation 230kV
Location
Imperial County, California
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 November 2011
Proposed online date
December 2014
Withdrawn
August 2012

Location

Marker shows the centre of Imperial County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Imperial County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem