United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

West Hill Windfarm

West Hill Windfarm is a 31.5 MW onshore wind request withdrawn in the NYISO interconnection queue, in Madison County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2004 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
147
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
NY Windpower, LLC
Connection point (POI)
Oneida-Fenner 115kV
Location
Madison County, New York
Technology
Wind: 31.5 MW
Total requested
31.5 MW
Queue status
Withdrawn
Entered queue
16 April 2004
Withdrawn
August 2012

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem