Solar project 733, Washington County

Solar project 733, Washington County is a 18.0 MW solar request withdrawn in the West interconnection queue, in Washington County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
733
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Red Butte substation at 34.5 kV
Location
Washington County, Utah
Technology
Solar: 18.0 MW
Total requested
18.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
14 March 2016
Proposed online date
December 2019

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Washington County