Solar project GEN-2021-SR2, Muskogee County

Solar project GEN-2021-SR2, Muskogee County is a 21.4 MW solar request withdrawn in the SPP interconnection queue, in Muskogee County, Oklahoma.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingOct 2022 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-SR2
Grid region
SPP (Southwest Power Pool)
Location
Muskogee County, Oklahoma
Technology
Solar: 21.4 MW
Total requested
21.4 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
12 February 2021
Proposed online date
October 2022
Came online
October 2022
Withdrawn
September 2021

Location

Marker shows the centre of Muskogee County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Muskogee County