United States › Grid › Interconnection queues › New Hampshire
SOLAR · ISO-NEEE Lost Nation Group DG Study
EE Lost Nation Group DG Study is a 10.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Coos County, New Hampshire.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2024 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1503
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- EE Lost Nation substation
- Location
- Coos County, New Hampshire
- Technology
- Solar: 10.0 MW
- Total requested
- 10.0 MW
- Queue status
- Withdrawn
- Entered queue
- 13 March 2024
- Proposed online date
- December 2025
- Withdrawn
- March 2024
Location
Marker shows the centre of Coos County; the queue data does not give exact sites.
Power plants in New Hampshire · Transmission lines in New Hampshire
Other requests in Coos County
- Granite Reliable PowerOnshore wind · 94.5 MW · built
- Burgess BioPowerOther · 58.7 MW · built
- GLHA James River/Fraser Paper7Hydro · 25.0 MW · built
- Berlin Energy Uprate and Battery AdditionOther · 15.0 MW · built
- Burgess BioPower IncreaseOther · 9.0 MW · built
- Jericho WindOnshore wind · 8.6 MW · built
- Jericho Wind expansionOnshore wind · 3.5 MW · built
- WindOnshore wind · 180 MW · withdrawn
- WindOnshore wind · 146 MW · withdrawn
- Solar + Battery StorageSolar + storage · 113 MW · withdrawn
- Biomass ProjectOther · 67.5 MW · withdrawn
- SolarSolar · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem