United States βΊ Grid βΊ Interconnection queues βΊ Michigan
BATTERY STORAGE Β· MISOBattery storage project J1860, Lenawee County
Battery storage project J1860, Lenawee County is a 60.0 MW battery storage request withdrawn in the MISO interconnection queue, in Lenawee County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedMar 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1860
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Morocco to Beecher 138kV (8.36 miles from Morocco)
- Location
- Lenawee County, Michigan
- Technology
- Battery: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 August 2021
- Proposed online date
- September 2024
- Withdrawn
- March 2025
Location
Marker shows the centre of Lenawee County; the queue data does not give exact sites.
Other requests in Lenawee County
- Solar project J1226, Lenawee CountySolar Β· 200 MW Β· under construction
- Solar project J875, Lenawee CountySolar Β· 150 MW Β· under construction
- Solar project J996, Lenawee CountySolar Β· 80.0 MW Β· under construction
- Solar project J1571, Lenawee CountySolar Β· 200 MW Β· agreement signed
- Onshore wind project J3313, Lenawee CountyOnshore wind Β· 263 MW Β· in study
- Battery storage project J4026, Lenawee CountyBattery storage Β· 250 MW Β· in study
- Onshore wind project J4120, Lenawee CountyOnshore wind Β· 200 MW Β· in study
- Solar project J4044, Lenawee CountySolar Β· 190 MW Β· in study
- Battery storage project J3651, Lenawee CountyBattery storage Β· 150 MW Β· in study
- Surplus; J875Other Β· 150 MW Β· in study
- Solar project J4061, Lenawee CountySolar Β· 150 MW Β· in study
- Onshore wind project J4126, Lenawee CountyOnshore wind Β· 112 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem