🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

BATTERY STORAGE · PJM

Clinton County Energy Storage Project

Clinton County Energy Storage Project is a 4.0 MW battery storage request built and operating in the PJM interconnection queue, in Clinton County, Ohio, connecting to DEOK.

Queue statusOperating
  1. PlanningQueued Oct 2014 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AA1-099
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Clinton Co. 34.5kV
Location
Clinton County, Ohio
Technology
Battery: 4.0 MW
Total requested
4.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 October 2014
Proposed online date
October 2016
Came online
August 2016

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Clinton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem