United States › Grid › Interconnection queues › Florida
SOLAR · SOUTHEASTSolar project 263, Palm Beach County
Solar project 263, Palm Beach County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Palm Beach County, Florida, connecting to Florida Power & Light.
Request details
- Queue ID
- 263
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Cedar-Corbett 230kV
- Location
- Palm Beach County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 27 June 2017
- Proposed online date
- January 2025
- Came online
- January 2025
Location
Marker shows the centre of Palm Beach County; the queue data does not give exact sites.
Other requests in Palm Beach County
- Solar project 260Solar · 74.5 MW · built
- Solar project 294, Palm Beach CountySolar · 74.5 MW · built
- Solar project 269, Palm Beach CountySolar · 74.5 MW · built
- Solar project 553, Palm Beach CountySolar · 74.5 MW · withdrawn
- Solar project 495, Palm Beach CountySolar · 74.5 MW · withdrawn
- Solar project 317, Palm Beach CountySolar · 74.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem