Seneca Pumped Storage Generating Station

Seneca Pumped Storage Generating Station is a 17.0 MW hydro request built and operating in the PJM interconnection queue, in Warren County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Oct 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingApr 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Z1-087
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Glade 230kV
Location
Warren County, Pennsylvania
Technology
Hydro: 17.0 MW
Total requested
17.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 October 2013
Proposed online date
December 2017
Came online
April 2017

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem